Jun 8, 2017 @ 12:11
One lane is open, alternating traffic is flowing.
Jun 8, 2017 @ 08:11
Travellers must continue to detour around the collapsed culvert at Poulin Creek just east of the Highway 129/101 Junction. The culvert failed Monday, June 5, 2017 in early morning as the culvert replacement was beginning. As the first sheet pile was being installed the culvert beneath the eastbound lane collapsed. A short time later, the westbound side collapsed as well.
The culvert replacement is taking longer than expected, with the highway possibly being re-opened late tonight or tomorrow morning.